Tool-trial governance

T0 and T1 sampling gates: define what each mould trial is allowed to prove.

Trial labels vary between programmes and suppliers. PartVerity defines the purpose, tool state, resin, process state, sample identity, evidence and named disposition authority for every trial instead of treating a T-number as automatic approval.

Decision premise

Trial question: what decision can this build support, and which open issues remain outside its evidence?

Engineering control

Six controls for traceable T0/T1 sampling

A trial is useful only when its configuration and expected decision are known before the press starts.

01

Gate definition

State whether the trial evaluates tool function, filling, appearance, dimensions, assembly, process window or a later approval objective.

Evidence route

Written trial plan, gate criteria and named approver

02

Tool configuration

Record tool revision, cavities, inserts, temporary steel, texture/polish, cooling, hot runner and known incomplete operations.

Evidence route

Tool-status sheet and dated configuration images

03

Material and process state

Identify exact resin/colour, drying, machine, settings, deviations and whether parameters are exploratory or controlled.

Evidence route

Material lot and trial process record

04

Sample genealogy

Mark samples by trial, cavity where relevant, time/shot range and post-processing so data cannot detach from configuration.

Evidence route

Sample ID map and retained/reference sample register

05

Evidence package

Collect defined dimensional, visual, functional and process observations with actual results and non-conformance status.

Evidence route

Trial report, ballooned results and issue log

06

Disposition and next gate

Separate information-only samples, conditional use, correction approval and production release; assign actions and retrial scope.

Evidence route

Signed disposition, action owners and next-trial plan

Decision matrix

Trial condition to permitted decision

T0/T1 terminology is not universal. The written programme definition governs.

Trial conditionUseful decisionNot yet proven
Initial tool functionCan the tool operate and produce reviewable parts?Stable dimensions or production repeatability
Exploratory process settingsWhich issues are tool- versus process-sensitive?Approved process window
Incomplete texture or steelGeometry/flow learning within stated limitsFinal appearance or locked dimensions
Dimensional sample buildCurrent cavity results against defined CTQsLot capability without repeat evidence
Post-correction retrialWhether approved actions closed named issuesUnreviewed changes outside retrial scope

Claim boundaries

Trial labels that need qualification

‘T1 approved’ is incomplete without the signed disposition scope.

Selected good samples do not represent the full trial run.

A dimensional report without tool, cavity and process identity is weak evidence.

Trial approval does not waive open cosmetic, functional or documentation issues.

Technical context

Use guidance to frame the review—not to replace project evidence.

External context for progressive sample stages. PartVerity treats every gate definition and release scope as project-specific.

EPower T0/T1/T2 sampling guide